NEDC contractors decry non-payment of balance

NEDC contractors decry  non-payment of balance

Contractors handling various projects for the North East Development Commission has appealed to the Federal Government to intervenecin the non-payment of contractors retention balance running into billions of naira

Some of the contractors that spoke to Arewa punch via phone on Monday on condition of annonimty said that their retention balance has exceeded the six months mandately time for final payment after completion of the project.

“Retention balance is a mandatory procedure after you complete a project, part of the contract sum will be held for the time frame of six months, so that if there is problems with the project you will be called back to resolve it”.

“Hundreds of us our retention balance period has expired over one year and yet we are not paid “he said.

“ Most of the contractors who handled solar borehole projects completed their work about 8-12 months ago have not receive their payments “.

Make PUNCH part of your everyday experience.Add us to your Preferred Sources

The contractors pointed that they were forced to abandoned majority of the  NEDC projects as a result of non-payment by the commission.

“Go round only in Adamawa state, you will see a lot of abandoned projects all over the 21 local governments, this is because we are not paid by the commission, “he said.

When Arewa punch visited the NEDC 500 housing project in Fofure local government which was awarded in 2022 under the government of late president Muhammadu Buhari, it is abandoned at the foundation level.

In Song local government also the special model School projects designed for the three senatorial district in Adamawa state was abandoned over five years ago.

In Modibbo Adama University Teaching Hospital Yola the project was abandoned and many other projects scattered in state.

When Arewa punch contacted the Adamawa state coordinator of NEDC Alhaji Kahlifa Lawan, he addmited that some projects were abandoned as a results of some challenges associated the projects.

“We have started mobilizing our contractors to go back to site, before the end of this month all our contractors will be fully on their site to complete those projects.

He urged the contractors to remain calm and corporate with the commission for the smooth completion of the projects for the good of the people of North East region,

Make PUNCH part of your everyday experience.Add us to your Preferred Sources

Stay informed and ahead of the curve! Follow The Punch Newspaper on WhatsApp for real-time updates, breaking news, and exclusive content. Don't miss a headline – join now!

Join The Punch Newspapers Channel

Stay in the know—fast. Get instant alerts, breaking headlines, and exclusive stories with the Punch News App. Download now and never miss a beat.

Get the Punch News App


Read PUNCH Anywhere

Unlock the full print replica on any device - every page, every day. Subscribe now for instant e-edition access.

Subscribe

Latest News