Electricity supply has been disrupted in parts of Port Harcourt, Rivers State, and its environs following a labour dispute involving the management of Afam IV Gas Power Station and the National Union of Electricity Employees.
The Transmission Company of Nigeria disclosed this in a statement signed by its management on Tuesday, adding that the disruption began on Monday, September 28, 2026, after members of the state’s NUEE chapter opened the Afam–Alaoji 330-kilovolt Transmission Line 2 at the Alaoji 330kV Transmission Substation.
The action, linked to the ongoing disagreement between the union and the management of the power station, affected the transmission of electricity to parts of Port Harcourt and neighbouring communities.
TCN said the incident caused the 150-megavolt-ampere 330/132kV inter-bus transformer at Afam IV to trip, disrupting bulk electricity transmission through the affected facilities.
The statement read, “The Transmission Company of Nigeria wishes to inform the public that parts of Port Harcourt and its environs are currently experiencing electricity supply disruption following a labour-related incident at Afam IV Power Station.
“The disruption started on Monday, September 28, 2026, when members of the National Union of Electricity Employees, Rivers State Chapter, opened the Afam–Alaoji 330kV Transmission Line 2 at the Alaoji 330kV Transmission Substation. The action is linked to an ongoing labour dispute involving the management of Afam IV Gas Power Station and NUEE. Consequently, the 150MVA 330/132kV inter-bus transformer at Afam IV tripped, affecting bulk electricity transmission to parts of Port Harcourt and its environs.”
The company said the affected infrastructure included the Port Harcourt Town 132kV Transmission Substation, Elelenwo 132kV Transmission Substation and the 60MVA 132/33kV transformer at the Port Harcourt Mains 132kV Transmission Substation.
The disruption highlights how labour disputes affecting critical power infrastructure can interrupt electricity supply to communities and businesses that depend on the national grid.
TCN said it was engaging relevant stakeholders, including the Nigerian Independent System Operator, to restore the affected facilities once conditions permitted safe restoration.
The company stated, “TCN is engaging relevant stakeholders, including the Nigerian Independent System Operator (NISO), to restore the affected facilities as soon as conditions allow safe restoration.”
It did not disclose the nature of the labour dispute or provide a specific timeline for the restoration of electricity supply to the affected areas.
The transmission company apologised to consumers for the disruption and said it would continue to provide updates as the situation developed.
“TCN regrets the inconvenience caused to electricity consumers in the affected areas and will continue to provide updates as the situation develops,” the statement added.
The development comes amid the operational challenges facing Nigeria’s electricity supply chain, where disruptions at generation plants or transmission facilities can affect power delivery to distribution companies and end users.
TCN is responsible for transmitting bulk electricity from generation stations to distribution networks, while NISO coordinates the operation of the national electricity grid.